As the commercial aircraft industry moves into the second-half of 2016, it is time for our usual Supply Chain Matters six month industry review of performance. Reflecting on delivery performance thus far, there are continued signs of industry supply chain supply challenges.  Airbus Mobile Alabama Manufacturing Facility

Let’s begin with Airbus which reported the booking of a total of 227 confirmed orders in the first six months of the year. That number may be somewhat understated since at the industry’s recently completed Farnborough Air Show, Airbus achieved bragging rights for announcing orders and commitments for 279 commercial aircraft, more than half originating from a single airline customer, that being AirAsia who ordered 100 A320neos.

 

Airbus recorded the delivery of a total of 298 aircraft in the first-half, which consisted of the following:

  • 160- Single aisle aircraft (Variants of A319, A320, A321)
  • 38- A330’s
  • 27- A350’s
  • 2- A380’s

 

In the above, tell –tale signs of supply disruption are reflected in two key aircraft. There were only 8 completed deliveries of the brand new A320neo, no doubt reflecting the ongoing catch-up in delivery of the brand new Pratt & Whitney geared turbofan engines.  Airbus had delivered just 5 A320neos in Q1 meaning that just 3 were delivered in Q2. As noted in our prior commentary, nearly a dozen of completed A320neos have been reported as lined-up on factory adjacent runways and parking areas awaiting Pratt to deliver completed engines. The exiting delay is associated with fixing the engine’s cooling design through a combination of software and component modifications.  Pratt engine deliveries were not expected to catch-up until after June and there are continued reports that Pratt’s supply chain remains strained.  The other new engine offering, the new LEAP model from CFM International is expected to be available in the second-half of this year as-well. With a stated target to have a production level of 50 A320neo’s per month by 2017, there is a lot more planning and execution remaining.

A further problematic area acknowledged by Airbus has been supply and bottleneck challenges associated with newest model A350 production, and first-half completion of 27 reflects that ongoing challenge. Supply challenges have been noted as interior seating and structures and Airbus senior management has expressed public frustration regarding ongoing supply glitches.

Turning to Boeing, the aircraft producer reported the booking of a total of 321 orders in the first-half. At the completion of the Farnborough event in July, Boeing was able to announce orders and commitments for 182 aircraft but just 20 actual new firm orders.

Boeing further recorded the delivery of a total of 298 aircraft reflecting its previously announced scaled-down expectations for delivery cadence this year. The breakdown was:

  • 248-737’s
  • 3-    747’s
  • 5- 767’s
  • 51- 777’s
  • 68- 787 Dreamliners

 

In the above, a challenged area remains completed deliveries of Dreamliners although the cadence has improved slightly beyond 10 per month. There is still a long way to go in ramp-up and lots of internal pressures remain since the program remains cash negative until delivery performance dramatically improves.  Both Boeing’s Seattle and South Carolina assembly facilities are now producing completed Dreamliners.

With current order backlogs of nearly ten years for Airbus and over seven years for Boeing at current production cadence levels, both manufacturers have been concentrating on increased production automation and longer-term strategic supplier agreements. In June, key suppliers urged both manufacturers to move cautiously on demand noting that there are definitive restrictions on the ability to ramp-up the industry supply chain to expected volume output cadence.  Another growing concern is the ability of aircraft engine producers to be able to support higher output volumes given the increased technical sophistication of the new generation engines.  Pratt alone is in the midst of managing five different new engine models and with both commercial aircraft dominant manufacturers continuing to book further orders and explore newer model introduction, the pressure builds.

Again, only time will prescribe the course of events in an industry that is clearly reflecting supply chain distress.

Bob Ferrari